5.0 Drainage Design and Construction Guidelines and Requirements
This section provides Drainage Design and Construction Guidelines and Requirements information that must be considered when preparing the design and implementation of land development works.
These guidelines extend to Melbourne Water Works only and the Consultant should contact the relevant local council for information about non-Melbourne Water drains.
Except where specified by Melbourne Water to the contrary, the Consultant is responsible for all aspects of the design of the Works. It is the Consultant's responsibility to justify any variation from the requirements set out in this document or otherwise specified by Melbourne Water.
- 5.1 Drainage System Objectives
- 5.2 General approach to drainage systems
- 5.3 Designing for stormwater conveyance
- 5.4 Stormwater Quality Management
- 5.5 At Source Treatment versus Regional Treatments
- 5.6 At Source Treatments (WSUD)
- 5.7 Waterway rehabilitation and protection
- 5.8 Vegetation management
- 5.9 Habitat management
- 5.10 Aquatic habitat management
- 5.11 Waterway interface with adjacent open space
- 5.12 Waterway crossings
- 5.13 Rockwork for waterway protection
- 5.14 Works adjacent to a Melbourne Water asset
- 5.15 Protecting human and environmental health