7.6 'As Constructed' Requirements
Melbourne Water requires the following:
- Survey Control (Registered PSM) information for the purpose of audits during or following completion of the Works
- CAD files: The original design plans should be annotated with 'as constructed' information and submitted in CAD format. For further details, refer to the form; As Constructed Survey Certification Checklist (PDF, 43kb).
- PDF files: Adobe PDF files are to be produced as an output of the 'as constructed' CAD files.
- Hardcopy plans: Licence Surveyor certified hardcopy plans are only required on relevant plans of as constructed information where an asset relates to a title. The hardcopy plan does not replace, but is in addition to the CAD and PDF files.
- Digital 'as constructed' Survey Information: survey information for centrelines/structures of assets must also be provided, as well as for features surveys, including wetlands, retarding basins and waterway rehabilitation works. For further details, refer to As Constructed Requirements for Digital Survey Information.